Via Campus Update
To the campus community:
As is required by New York State Law, we are preparing to carry out our annual fire alarm system inspection and testing for the College. This very important measure is conducted each year to ensure that our fire alarm systems are operating properly. Accordingly, we contract with an independent certified fire alarm testing and inspection company who will conduct the required tests on each fire alarm device, in each building, campus-wide.
Beginning Monday, May 4th and continuing until September, the technicians will follow the attached schedules as closely as practicable, carrying out the tests and inspections between 7:00 am – 3:30 pm. Where possible, the contractor will make building-wide broadcast announcements and display signage announcing all testing.
In the event that a fire alarm activates in a building where testing is not scheduled AND announcements and postings do not identify testing occurring within, please treat the alarm as authentic and evacuate.
Due to the potential for unanticipated delays the attached schedules are not set in stone, and adjustments will take place without email notification. ***NOTE: As these systems are designed to preserve life and property, repairs to any identified deficiencies will be carried out when appropriate, as determined by the contractor. This means there may be technicians in your building on days other than those listed in the attached schedule. Audible and visual alarm tests will be carried out during the times that will cause the least inconvenience to building occupants.
Thank you so very much for your understanding during this very important safety project.
Scott F. Schulte, CEM
Director, Office of Emergency Management
Service Building, Suite 217
(845) 257-2387
May 2020
SUNY NEW PALTZ ANNUAL FIRE ALARM INSPECTION AND TESTING SCHEDULE
May 2020 |
||||||
Sun |
Mon |
Tue |
Wed |
Thu |
Fri |
Sat |
|
|
|
|
|
1 |
2 |
3 |
4 STUDENT
UNION & ATRIUM |
5 STUDENT
UNION & ATRIUM |
6 ESOPUS HALL |
7 BLISS HALL |
8 CAPEN HALL |
9 |
10 |
11 MOHONK HALL |
12 LENAPE HALL |
13 GAGE HALL |
14 COLLEGE/ SHANGO HALL |
15 COLLEGE/ SHANGO
HALL |
16 |
17 |
18 ASHOKAN HALL |
19 RIDGEVIEW HALL |
20 SHAWANGUNK HALL |
21 MINNEWASKA HALL |
22 AWOSTING
HALL |
23 |
24 |
25 SCUDDER HALL |
26 PARKER
& TERRACE |
27 SOUTH FACULTY |
28 ELTING GYM |
29 ELTING GYM |
30 |
31 |
|
June 2020
SUNY NEW PALTZ ANNUAL FIRE ALARM INSPECTION AND TESTING SCHEDULE
June 2020 |
||||||
Sun |
Mon |
Tue |
Wed |
Thu |
Fri |
Sat |
|
1 RESNICK HALL |
2 FINE ARTS BLDG |
3 FINE ARTS BLDG |
4 HEALTH CENTER |
5 FACULTY OFFICE BLDG |
6 |
7 |
8 MCKENNA & DORSKY |
9 SMILEY ART BLDG |
10 SMILEY ART BLDG |
11 CENTRAL HEATING PLANT |
12 PEREGRINE DINING HALL |
13 |
14 |
15 SOJOURNER TRUTH LIBRARY |
16 SOJOURNER TRUTH LIBRARY |
17 JACOBSON FACULTY TWR |
18 OLD LIBRARY & WAREHOUSE 5 |
19 GRIMM & GROUNDS |
20 |
21 |
22 HAGGERTY ADMIN BLDG |
23 HAGGERTY ADMIN BLDG |
24 SOUTH CLASSROOM |
25 SERVICE BUILDING |
26 WOOSTER HALL |
27 |
28 |
29 WOOSTER HALL |
30 COYKENDALL SCIENCE |
|
July 2020
SUNY NEW PALTZ ANNUAL FIRE ALARM INSPECTION AND TESTING SCHEDULE
July 2020 |
||||||
Sun |
Mon |
Tue |
Wed |
Thu |
Fri |
Sat |
|
|
|
1 COYKENDALL SCIENCE |
2 VAN DEN BERG & ANNEX |
3 VAN DEN BERG & ANNEX |
4 |
5 |
6 HUMANITIES |
7 HUMANITIES |
8 OLD MAIN |
9 OLD MAIN |
10 ATHLETIC WELLNESS |
11 |
12 |
13 ATHLETIC WELLNESS |
14 SCIENCE HALL |
15 SCIENCE HALL |
16 CHILD CARE CENTER |
17 HOPFER (BEFORE 8:00) |
18 |
19 |
20 DASNY & SUCF |
21 REPAIRS & RETESTS |
22 REPAIRS & RETESTS |
23 REPAIRS & RETESTS |
24 REPAIRS & RETESTS |
25 |
26 |
27 REPAIRS & RETESTS |
28 REPAIRS & RETESTS |
29 REPAIRS & RETESTS |
30 REPAIRS & RETESTS |
31 REPAIRS & RETESTS |
|
August 2020
SUNY NEW PALTZ ANNUAL FIRE ALARM INSPECTION AND TESTING SCHEDULE
August 2020 |
||||||
Sun |
Mon |
Tue |
Wed |
Thu |
Fri |
Sat |
|
|
|
|
|
|
1 |
2 |
3 REPAIRS & RETESTS |
4 REPAIRS & RETESTS |
5 REPAIRS & RETESTS |
6 REPAIRS & RETESTS |
7 REPAIRS & RETESTS |
8 |
9 |
10 REPAIRS & RETESTS |
11 REPAIRS & RETESTS |
12 REPAIRS & RETESTS |
13 REPAIRS & RETESTS |
14 REPAIRS & RETESTS |
15 |
16 |
17 REPAIRS & RETESTS |
18 BOUTON HALL |
19 BOUTON HALL |
20 LECTURE CENTER |
21 LECTURE CENTER |
22 |
23 |
24 REPAIRS & RETESTS |
25 REPAIRS & RETESTS |
26 REPAIRS & RETESTS |
27 REPAIRS & RETESTS |
28 REPAIRS & RETESTS |
29 |
30 |
31 REPAIRS & RETESTS |
|